Why right-of-way is the most important schedule driver in pipeline projects

 

When a gas utility or pipeline company decides to expand its system, the first instinct is to focus on engineering, route design, pipe specs, construction timelines. But experienced project teams know that a different workstream quietly drives the entire schedule: Right-of-way (ROW) acquisition. Get it right, and a project moves efficiently from planning to construction. Get it wrong, and costs escalate, timelines slip, and community relationships fracture in ways that are difficult to repair.

What ROW acquisition involves

At its core, ROW acquisition is the process of securing legal agreements and rights, typically in the form of an easement or surface lease, for a pipeline to cross private land and permit for crossing public land. Unlike a fee purchase, an easement allows the landowner to retain ownership and continue using their property; it simply grants the pipeline operator the right to install, operate, maintain, and access the line in a defined location. Once the pipeline is in the ground, it is unseen and landowners can farm over it, pave over it, and continue using the surface as before, as long as their use does not hinder the operation and maintenance of the pipeline.

But the work involved in getting there is anything but simple. A large pipeline project can cross hundreds or even thousands of individual parcels, each with its own ownership structure, title history, liens, and stakeholder dynamics. The ROW team must research every parcel, identify every interest holder, make initial contact with landowners, secure survey access, accompany field crews, and negotiate easement agreements, all while serving as the public face of the project.

There is also a construction phase where ROW agents remain active during construction to notify landowners ahead of crew arrivals, manage any surface damage claims, and resolve issues that may arise if equipment strays outside its permitted footprint.

Why ROW is a critical path activity

In project planning, a “critical path” activity is one where any delay directly impacts the overall project schedule. ROW acquisition earns that designation for several reasons.

First, construction cannot begin until the easements and permits are secured. No easement, no pipe in the ground. Second, ROW timelines are inherently unpredictable. Landowner negotiations can stall, title research can surface unexpected complications, and eminent domain proceedings, when necessary, add legal timelines that no team controls. Third, cost implications are significant. Easement acquisition costs, appraisal fees, legal expenses, and potential condemnation proceedings must all be estimated and budgeted well in advance, often years before a shovel hits the ground.

Finally, landowner and community opposition is a consistent source of project friction. As Gary Bland, Director at Atwell in the Houston office, notes “Pipeline projects aren’t always the most popular thing to introduce into a community. It’s a necessary and important function though in cities, towns and rural communities everywhere.” That reality shapes everything about how a ROW campaign should be planned and executed. Proactive, transparent engagement with affected property owners and community leaders is one of the most powerful tools a project team has.

Essential strategic steps before field deployment

By the time a ROW agent knocks on the first door, the outcome of the campaign is often already set.  Effective pre-deployment preparation includes several interconnected activities. Route analysis and landowner identification using GIS and public data to evaluate alignment options, estimate parcel counts, assess property types and values, and identify existing infrastructure corridors that might reduce the footprint on undisturbed land. Title research and ownership verification ensure that when a ROW agent sits across the table from a landowner, they understand every interest in that property (ownership, mortgages, liens, and other encumbrances) that could affect the agreement. Cost estimation must account not just for today’s land values but projected values across a multi-year project timeline.

Community and stakeholder outreach, ideally beginning with elected officials and community leaders, ensures that key voices hear the project’s story directly. Bland is direct on this point: ” The worst outcome is when community leaders hear about a project from concerned constituents instead of directly from you. Hearing it from you first sets the right tone from the start.” Stakeholders who feel informed and respected are far more likely to facilitate, rather than oppose, a project moving forward.

The advantage of integrated services

One factor that meaningfully improves ROW outcomes is the integration of land, survey, engineering, and environmental services under a single coordinated project team. These disciplines are deeply interdependent. ROW agents must secure survey access before field crews can mobilize. Surveyors need title information to thoughtfully plan their work. Land acquisition teams need finalized survey plats before they can execute binding agreements with landowners.

When these functions operate in silos, with separate vendors pursuing their own timelines, handoffs break down. As Bland describes it: “You’re often going to have a breakdown. They’re not focused on working with others but rather on keeping their tasks on time.”

By contrast, when land, survey, and environmental teams are aligned from day one, the project moves as a single, coordinated effort rather than  a collection of competing priorities. Data is shared in real time, schedules are aligned, and accountability is clear, giving clients greater confidence that every piece of the project is moving forward together. Bland notes that success and trust come from that kind of execution: “Projects are successful when all disciplines work closely and that’s often how we see long-term relationships grow.”

Long term projects illustrate the complexity of ROW

A current Atwell engagement illustrates this at scale. A gas distribution utility is planning a trunk line system of more than 300 miles, designed to serve the region’s continued outward growth. The project will cross approximately 3,000 parcels and is expected to span several years, with construction advancing in preplanned annual segments determined by growth projections.

The work currently underway is precisely the kind of pre-deployment preparation described above: building GIS-based ownership inventories, routing alignments to minimize impact, engaging appraisers for multi-year cost projections, and beginning outreach to community leaders. The utility’s public-facing profile has made stakeholder communication a priority and that posture has created space to approach the work the right way. “They’re really focused on their public reputation and quality engagement,” Bland notes, “so it allows us to spend more time and effort to try to make this effort a win for the community.”

Preparation is the project

ROW acquisition is not a checkbox, it’s a sustained, relationship-driven discipline that shapes every aspect of a pipeline project. Teams that treat it as a strategic function, and invest early, consistently outperform those that treat it as an afterthought. In a business where projects take years and mistakes are costly, that difference isn’t minor, it’s everything.